Insure the finished value of the work, not today’s value. Decide early whether hail and wind carry their own deductible on a roof that is not yet complete, plan for a hard freeze before the building is closed in, and price soft costs if a lender or future tenants are counting on a completion date. I insure the project; I do not build it.
Completed value or a reporting form
Most single Dallas projects, such as a garden apartment complex, a tilt-wall distribution building or a custom home in Preston Hollow, are written on a completed value basis: the limit is what the work will be worth when it is done, and the premium is set on that number from day one. The policy does not grow with the job, so the starting limit has to be right.
- Build the number from the contract. The contract sum, approved change orders, owner-furnished items such as appliances or light fixtures, and site work you want covered.
- Ask about soft costs separately. Architect’s fees, permit costs and the builder’s fee are left out of many limits unless they are listed.
- Production builders with houses going up across several subdivisions usually fit a reporting form better, where each start is declared and values are reported on a schedule. Late reports are the classic way to end up underinsured on that form.
Q-Team reviews, floodplain permits and when coverage starts
Dallas Development Services runs a fee-based Q-Team for commercial projects that want a faster path to a permit: an appointment-only meeting with the applicant, the design team and city reviewers from zoning, building code, fire, engineering and other disciplines, aimed at getting the project to permit issuance. The city’s list of projects that do not qualify includes sites that are not properly zoned or platted and projects still waiting on floodplain, historic or conservation approvals.
Floodplain sites have a longer road. The City of Dallas says a floodplain fill permit is required to reclaim floodplain land for development, and that construction of a new structure requires both that permit and final approval by the Dallas City Council. Retaining walls, pools, fences and landscaping in the floodplain need a floodplain alteration permit instead.
- Bind before the first delivery, even if the permit is still in review. Stored materials are part of the risk.
- Set the term to the real schedule, including Council timing on a floodplain lot, and ask now how an extension is priced.
- Flood is its own question. On a site in or near the floodplain, ask whether the builder’s risk form covers flood at all and at what sublimit. Commercial flood coverage.
Building to the 2021 codes, and renovating under the existing-building code
The City of Dallas lists the 2021 International Building Code, 2021 International Residential Code and 2021 Energy Conservation Code, each with Dallas amendments, as effective May 12, 2023, and the 2021 International Existing Building Code as effective June 13, 2022. The edition your permit is issued under drives what the finished building costs, which is the number the builder’s risk limit should match.
A renovation adds a second piece of property to the conversation: the building that is already standing. Many builder’s risk forms insure only the new work, so an office repositioning or a gut renovation of an older apartment building may need existing-structure coverage added, or the owner’s property policy kept in force and endorsed to allow the work. If a covered fire damages the old building during the job, repairs may also have to meet current code; that cost is ordinance or law coverage, which is limited unless you buy more.
Hail, wind and freeze before the building is closed in
- Hail and wind. North Texas underwriters often write a separate wind and hail deductible, sometimes as a percentage of the project value. On a building where the roof membrane, windows or façade panels are half-installed, that deductible decides whether a spring storm is a claim or a cost. Read it before the policy is bound.
- Freeze. February 2021 showed every Texas builder what a long freeze does to a building with plumbing and fire sprinkler lines installed but no permanent heat. Many forms limit freeze or water losses unless reasonable steps were taken, such as draining lines or keeping temporary heat on. Write down the cold-weather plan and keep it with the job file.
- Water damage. Water is one of the most common builder’s risk losses in general: a failed fitting during testing, rain through an open roof deck, a broken sprinkler head. Ask what the water damage deductible is, because it is often higher than the base deductible.
For the finished building’s long-term property terms, see commercial property insurance in Dallas.
Soft costs and delay when the opening date matters
On a financed apartment or commercial project, the expensive part of a fire may be the months it adds. Soft cost and delay in completion coverage can pay items such as additional construction loan interest, extra professional fees, re-leasing costs and, if it is bought by name, rent the owner would have collected. It is an optional coverage with its own limit and a waiting period, and it answers only to physical damage from a covered cause. A slow review or a late inspection is not a covered cause.
- The owner is the party with the delay loss, so the owner should be a named insured on that part.
- The lender usually wants to be named as loss payee or mortgagee; send me the loan agreement’s insurance section.
Theft, tools and testing on a Dallas site
- Materials theft. Copper wire, appliances and stored fixtures are what a builder’s risk policy protects. Underwriters ask about fencing, lighting, cameras and locked storage, and some forms exclude theft of materials not yet installed unless the site is secured.
- Contractor’s equipment. Tools, scaffolding, generators and rented machinery are generally excluded from builder’s risk and belong on the contractor’s own equipment policy. Tools and equipment coverage.
- Testing and commissioning. Ask whether the form covers damage during hot testing of HVAC, electrical and fire systems, and when coverage ends: at occupancy, at substantial completion or when the owner starts using part of the building.
- The contractor’s own program still matters: liability, auto and comp. Contractor insurance in Dallas.
What to send me
- The address and whether the site is in or near a mapped floodplain.
- The project: type, stories, square footage, construction type (wood frame, tilt-wall, steel, concrete) and any existing building being renovated.
- Completed value, broken into hard costs and the soft costs you want insured.
- Schedule: first delivery, framing or steel, dry-in and completion.
- The contract’s insurance section and the lender’s requirements.
- Site security and the cold-weather and water-testing plan.
Common questions
Do you have an office in Dallas?
No. Alishahi Insurance has one office, in Beverly Hills, California. I am licensed in Texas and place builder’s risk for Dallas projects by phone, text and email.
When should builder’s risk start on a Dallas project?
Before the first material delivery, not when vertical construction begins. Materials stored on site or in transit are part of what the policy covers.
Does builder’s risk cover hail damage to a roof that is not finished?
Hail is usually a covered cause, but many Texas policies carry a separate wind and hail deductible, sometimes a percentage of the project value. Read that deductible before binding.
Does builder’s risk cover flood on a Dallas floodplain site?
Not automatically. Some forms exclude flood and others cover it at a sublimit. A site that needed a floodplain fill permit should have that question answered in writing.
Will builder’s risk pay for delays in plan review?
No. Delay coverage responds to covered physical damage that pushes back completion, not to a slow permit review or Council schedule.
Who buys builder’s risk, the owner or the general contractor?
Either one, as the construction contract decides. Whoever buys it, the owner, the GC, the subcontractors and the lender should be on the policy as the contract requires.
General information about builder’s risk insurance for Dallas construction as of November 2026, not legal advice. City codes, floodplain rules and Development Services programs change; confirm your project’s requirements with City of Dallas Development Services and Dallas Water Utilities, and read your own contract and policy wording. Coverage depends on underwriting and the terms, conditions and exclusions of the policy actually issued.