A Nashville project is underwritten on the structure type (wood frame, podium, concrete or mass timber), the winter plan, the site and stormwater work, and how the wind and hail deductible is written in a city that has taken several tornadoes. Flood near the Cumberland and its creeks is usually excluded or sublimited and needs its own answer.
What builder’s risk covers on a Nashville project
The policy insures the building as it goes up and the materials and fixtures that will become part of it, on site and, depending on the form, in transit and in storage. It usually runs at the full completed value from the start of work until the owner accepts the building.
- Completed value or reporting form. One project usually means completed value. A home builder or developer with several jobs may report values monthly instead.
- Soft costs and delay. If a covered loss delays opening, the construction loan interest, fees and, on a hotel or apartment project, the lost income keep running. That coverage is added by endorsement with its own limit and waiting period.
- Testing. Commissioning of mechanical and electrical systems may need an endorsement. Some forms exclude damage to the equipment under test.
- Theft and vandalism. Materials and fixtures waiting to be installed are covered on most forms, often with conditions about fencing, lighting and locked storage.
Winter on an open building
The Weather Service’s account of the January 14 to 21, 2024 storm describes several days below freezing before temperatures rose just above it on January 18, and another drop to 4 degrees at the airport on the morning of January 21. Freeze losses on a project usually come from the same few places:
- Charged sprinkler and domestic water lines in floors that are not yet heated or closed in.
- Temporary heat that fails overnight, or runs without anyone checking it.
- Concrete, masonry and finishes placed before a hard freeze without protection.
- Water from the thaw moving down through floors and damaging finished work below.
Water damage is one of the most frequent builder’s risk losses, and some forms carry a separate, higher water deductible or conditions about heat and monitoring. Write down who checks the building on cold nights and how, and ask me to show you the water and freeze wording before you bind.
Mass timber and the fire question
Metro adopted mass timber standards in 2023 under Ordinance BL2023-1994, signed August 4, 2023 and based on the 2021 International Building and Fire Codes. Metro Codes says the old local cap was six stories, and certain mass timber types may now go up to 18.
A finished mass timber building has fire protection built in. Under construction it is a large amount of exposed wood before the protection is complete, and underwriters ask about it in detail:
- How far exposed timber is allowed to run ahead of noncombustible protection and working sprinklers.
- Standpipes and water supply as the building rises.
- Moisture protection for panels and beams on site and in the structure, since water-damaged timber may have to be replaced.
- Lead times. Replacement panels may come from a single plant far away, which lengthens any delay after a loss and makes the soft-cost limit matter more.
The same questions, on a smaller scale, apply to the wood-frame apartment buildings that make up much of the city’s new housing.
Grading permits and site work
Metro Water Services requires a grading permit from its Stormwater Division for land disturbance. The exemption applies only when the area disturbed at one time is 10,000 square feet or less and is not in a natural drainage way such as a designated floodplain, and exempt work still has to follow erosion and sediment control rules.
For the policy, that means most commercial projects include site work that can be damaged before the site is stabilized: storm pipes, detention, retaining walls, graded slopes. I check whether site work is in the insured value, how the form treats washout and earth movement, and whether flood is excluded or sublimited. A site near the Cumberland or one of its creeks needs flood addressed separately. Commercial flood insurance.
Tornado, wind and hail
Nashville has had damaging tornadoes in 1998, 2020 and 2023, and spring thunderstorms bring wind and hail most years. A frame that is up but not braced and sheathed is at its most vulnerable.
- Know the wind and hail deductible. On a large project it may be a percentage of the value at the time of loss.
- Per building or per occurrence. On a multi-building apartment project, how the deductible applies can change the number a great deal.
- Bracing and tie-down plans for tall walls, cranes and stored materials when a storm is forecast.
How wind and hail deductibles work.
Renovations, wraps and equipment
Existing buildings. Converting an older warehouse or office on the east side or downtown means insuring the existing structure as well as the new work. The standard form covers the new work; the existing building stays on the owner’s property policy or is added by endorsement. Commercial property insurance in Nashville.
Wrap-ups. An owner- or contractor-controlled program on a large project covers liability and workers’ comp; builder’s risk is usually bought beside it.
Equipment. Cranes, lifts and tools need the contractor’s own equipment coverage. Nashville contractor insurance.
What to send me
- The address, the project type and whether it is ground-up or renovation.
- Completed value, with site work and owner-supplied items shown.
- Construction type: wood frame, podium, concrete, steel or mass timber, and the number of stories.
- Soft costs you want covered and the lender’s requirements.
- Winter plan: temporary heat, who checks it and when sprinkler lines are charged.
- Schedule: start, dry-in, sprinklers in service and completion.
- The contract clause that says who buys the policy.
Call or text (877) 711-4545.
Common questions
Do you have an office in Nashville?
No. Alishahi Insurance has one office, in Beverly Hills, California. I am licensed in Tennessee and place builder’s risk for Nashville projects by phone, text and email.
Does builder’s risk cover frozen pipes on a building under construction?
Usually, subject to the policy’s conditions about heat and monitoring and any separate water deductible. Ask to see that wording before you bind.
Can I insure a mass timber building under construction?
Yes. Expect detailed questions about exposed timber, sprinklers, standpipes and moisture protection, and plan for longer replacement lead times in the soft-cost limit.
Do I need a grading permit in Nashville?
Metro Water Services requires one for land disturbance unless the area disturbed at one time is 10,000 square feet or less and outside a natural drainage way such as a floodplain.
Is tornado damage covered by builder’s risk?
Wind is a covered cause of loss on standard forms. What varies is the wind and hail deductible, which may be a percentage of the project value.
Is flood covered on a Nashville project?
Most builder’s risk forms exclude flood or give it a small sublimit. A site near the Cumberland or a creek needs flood addressed separately.
General information about builder’s risk insurance for Nashville construction as of November 2026, not legal advice. Metro codes, mass timber rules and Metro Water Services permit requirements change; confirm your project’s requirements with Metro Codes and Metro Water Services, and read your own policy wording. Coverage depends on underwriting and the terms, conditions and exclusions of the policy actually issued.