Energize Denver sets energy targets for buildings of 25,000 square feet and larger, and in April 2025 the city moved the interim and final deadlines to 2028 and 2032. When a covered building replaces its heating or cooling systems, the city expects electrification to be considered. Elevators and escalators are permitted through the Fire Department’s Fire Prevention Division and renewed every year. Each of those changes what a breakdown loss costs and what an underwriter asks.
What a Denver office building gets asked
- Energy targetsEnergize Denver’s interim and final deadlines for buildings 25,000 square feet and up are now 2028 and 2032.
- System replacementsThe city’s energy code guidance says covered buildings face electrification when systems are replaced.
- Elevator permitsThe Fire Department’s Fire Prevention Division runs the conveyance program, with annual renewal.
- HailFlat roofs, rooftop units and skylights take the hits; the wind and hail deductible decides the cost.
- Empty floorsVacancy clauses, freeze risk and an Energize Denver hold for buildings in short-term trouble.
- ConversionsThe city has piloted office-to-housing projects in Upper Downtown since 2023.
The coverage parts are explained on the office building page. This is the Denver part, as of November 2026.
Energize Denver, deadlines and the equipment you replace
City Council passed the current Energize Denver ordinance unanimously on November 22, 2021, building on a 2016 benchmarking law. As Facilities Dive reported, amendments approved on April 1, 2025 moved the interim and final target deadlines to 2028 and 2032, capped any building’s required energy cut at 42 percent, and pushed performance penalties back to late 2029. The same changes added a two-year hold for short-term circumstances such as vacancy or financial distress, and a 10 percent bonus on the efficiency target for buildings that get 80 percent or more of their energy from electricity.
The insurance point is in the mechanical room. The city’s guidance for existing commercial buildings says buildings of 25,000 square feet and larger face electrification upon system replacements, and that new or replacement gas-fired furnaces and unitary units have to meet specific energy code sections. If a boiler cracks or a rooftop unit fails, the claim may not be a like-for-like swap. I look at:
- The equipment breakdown form, and whether it pays anything toward a more efficient or electric replacement, or only like kind and quality.
- Ordinance or law limits on both the property and breakdown policies (how ordinance or law coverage works).
- Expediting expense, because a heat pump or chiller that has to be ordered in January leaves tenants cold for weeks.
Energize Denver compliance itself is not an insured risk. What insurance can do is keep a mechanical failure from becoming a code-driven rebuild you pay for alone.
Elevators, the conveyance program and liability
Denver’s conveyance page puts management and enforcement of conveyance inspections within the City and County of Denver under the Fire Department’s Fire Prevention Division. Owners apply through the city’s e-permit system, pay the fees and receive the record documents, and the page is direct about the cycle: conveyances must be renewed annually. Licensed conveyance contractors and third-party inspectors are listed by the department.
Underwriters want the current renewal, the latest inspection report and the maintenance contract. An elevator that traps or injures someone is a general liability claim, so the contract should require the elevator company to carry its own liability and to name you as additional insured. The machinery itself, from traction motors to controllers, is equipment breakdown territory, along with switchgear, boilers and chillers. A mid-rise with one passenger car can lose tenants quickly when that car is down, so I size the breakdown policy’s rent coverage to the building, not to a default.
Hail on a flat roof full of equipment
Hail history for the metro is covered on my Denver commercial property page. On an office building the damage list is longer than the membrane: condenser coils, rooftop unit housings, skylights, curtain wall and the cars in the garage deck. Three things in the quote matter most:
- The wind and hail deductible, whether it is a flat amount or a percentage of the building value, and whether it applies per building on an office park.
- How the roof is valued, replacement cost or actual cash value, and whether cosmetic damage to metal panels is excluded.
- Rooftop equipment, scheduled with the building and covered for hail, and roof drains kept clear so a storm does not turn into an interior water loss.
Send roof surveys with dates, and the record of what was replaced after past claims. How wind and hail coverage works.
Empty floors and conversions
A building that loses tenants can change its insurance before the owner notices. Most property forms restrict theft, vandalism, sprinkler leakage and water damage once a building has been largely empty for a stated period, and Denver’s cold makes heat in vacant suites a condition underwriters ask about (how vacancy affects a commercial policy). The Energize Denver hold for vacancy helps with the energy deadline; it does nothing for the property policy.
The city has also pushed conversions. CBS Colorado reported in August 2023 that the Adaptive Reuse Pilot Program in Upper Downtown gives applicants a dedicated project coordinator through review and permitting. If you take an office building down to the frame, builder’s risk covers the new work, but the existing structure needs coverage too, and I want it on replacement cost on one policy or the other, with the construction contract saying which. After the units are leased, the building is underwritten as housing.
Tenant improvements and loss of rents
Office leases put money into the walls. Build-outs usually become part of the real property, so if the building limit leaves them out and the tenant’s policy does not pick them up, a fire can leave nobody insuring the finished space, and the coinsurance clause can cut your recovery. I read each large lease to see who insures improvements and betterments, then set the building limit to match.
Loss of rents should cover base rent and the operating expenses tenants reimburse, for the full time a repair and re-leasing would take after a serious loss. An extended period of indemnity covers the months after the building reopens and before the space fills again. Tenant build-outs are also where water damage starts: require contractors on improvement jobs to carry liability with you as additional insured, and collect the certificates before work begins.
Terrorism, liability and the umbrella
Treasury’s Terrorism Risk Insurance Program is set to run through December 31, 2027; check whether Congress has extended it before a renewal runs past that date. Insurers must offer terrorism coverage, but owners are not required to buy it, so on a downtown tower the answer usually comes from the loan documents and the anchor leases (how TRIA coverage works).
The casualty side starts with general liability for lobbies, garages, plazas and stairwells, adds security and assault exposure in a building open to the public, and sits under a commercial umbrella and excess layers that should reach the highest limit any lender or lease requires. Colorado’s premises liability rules are set out on my Denver landlord page.
What to send me
- Address, year built, stories, square footage and construction type, with sprinkler and alarm details.
- Your Energize Denver status: benchmarking filings, target, any timeline adjustment or hold.
- The mechanical inventory: boilers, chillers, rooftop units, switchgear and their ages.
- Conveyance renewals and the elevator maintenance contract.
- Roof surveys and hail claim history, with what was replaced.
- The rent roll, with lease expirations, vacant suites and each lease’s insurance clause.
- Loan insurance requirements, including terrorism and umbrella limits.
- Current declarations pages and five years of loss runs.
Call or text (877) 711-4545. From outside the U.S. or Canada: +1 (424) 552-4545.
Common questions
Do you have an office in Denver?
No. Alishahi Insurance has one office, in Beverly Hills, California. I am licensed in Colorado and work with Denver building owners by phone, email and online.
When are the Energize Denver deadlines for an office building?
For buildings of 25,000 square feet and larger, amendments approved in April 2025 moved the interim and final target deadlines to 2028 and 2032. Check your building’s own target and any approved adjustment with the city.
Does insurance pay for an electric replacement if my boiler fails in Denver?
It depends on the equipment breakdown and ordinance or law wording. Some forms pay only like kind and quality, so a code-driven upgrade can fall on you unless the policy includes it.
Who inspects elevators in a Denver office building?
The Denver Fire Department’s Fire Prevention Division manages the conveyance program in the City and County of Denver, and conveyances must be renewed every year.
Does Energize Denver give a break for a vacant building?
The 2025 amendments added a two-year hold for short-term circumstances such as vacancy or financial distress. The property policy’s vacancy clause is a separate issue and still applies.
Do I need terrorism insurance on a Denver office tower?
No law requires it, but insurers must offer it, and lenders and large tenants often ask for it. The federal program’s current end date is December 31, 2027.
General information about insuring office buildings in the City and County of Denver as of November 2026, not legal or engineering advice. Energize Denver rules, energy code requirements, the conveyance program and the federal terrorism program change; confirm your building’s obligations with the Office of Climate Action, Sustainability and Resiliency, Community Planning and Development and the Fire Department. Coverage depends on the policy issued. Coverage depends on underwriting and the terms, conditions and exclusions of the policy actually issued.