Short answer: The City of Los Angeles requires two kinds of older buildings to be seismically strengthened or demolished. Wood-frame soft-story buildings (permit for the new building applied for before January 1, 1978, with parking or other open space at ground level and one or more stories above) get an order to comply and then have 2 years to submit plans, 3.5 years to pull permits and 7 years to finish. Non-ductile concrete buildings (permit application for the new building submitted before January 13, 1976, the date in the city code; LADBS's program page says January 13, 1977) get 3 years to submit a checklist, 10 years to submit retrofit or demolition plans, and 25 years to finish. The Los Angeles Department of Building and Safety (LADBS mandatory retrofit programs) records a notice against the property, and selling the building does not restart the clock. Insurance doesn't pay for a required retrofit. It matters during construction, for lost rent, and for the earthquake you're preparing for.
Who this affects
Owners of older apartment buildings with tuck-under parking, mixed-use buildings with storefronts or carports on the ground floor, condominium associations, and owners of older concrete office, retail, hotel, warehouse and parking structures inside the City of Los Angeles. Lenders, buyers and property managers are affected too, because the order is recorded and travels with the title. Both programs were created by Ordinance No. 183893. The soft-story time limits were later changed by Ordinance No. 184081, and Ordinance No. 186,583 (effective April 30, 2020) moved the concrete scope date in LAMC 91.9502 from January 13, 1977 to January 13, 1976. LADBS's program page and owner guide still give January 13, 1977, so if a building's permit date falls between the two, ask LADBS which applies.
This page covers only the City of Los Angeles. Other California cities have their own programs with different scopes and dates.
The two programs side by side
| Item | Wood-frame soft-story (LAMC Div. 93) | Non-ductile concrete (LAMC Div. 95) |
|---|---|---|
| Buildings in scope | Wood frame, permit for the new building applied for before Jan. 1, 1978 (or, with no permit on file, built under codes enacted before that date), with one or more stories over ground-floor parking or similar open space (soft, weak or open-front walls) | Concrete buildings whose roof or floors are carried by concrete walls or columns, built under a permit application for a new building submitted before Jan. 13, 1976 (or, with no permit on file, built under codes enacted before that date); LADBS's program page says Jan. 13, 1977 |
| Main exclusions | Residential buildings with 3 or fewer units used solely as residences | Detached single-family homes and duplexes |
| Step 1 | 2 years from the order: proof of previous retrofit, or retrofit or demolition plans | 3 years: checklist so LADBS can decide whether the building is non-ductile concrete |
| Step 2 | 3.5 years: permit to start construction or demolition | 10 years: proof of previous retrofit, or retrofit or demolition plans |
| Finish | 7 years: construction complete | 25 years: construction complete |
| Design level | 75% of the ASCE 7 base shear; new concrete or masonry walls and steel braced frames not allowed as the strengthening system | 75% of current LA code base shear (plus full drift checks for elements not part of the lateral system), or the ASCE 41 Basic Safety Objective |
| Contact | Soft-Story Retrofit Unit, (213) 482-7638 | Non-Ductile Concrete Retrofit Unit, (213) 978-4475 |
| Source | LADBS soft-story page; Ord. 184081 | LADBS non-ductile concrete page; LAMC 91.9502 as amended by Ord. 186,583; Ord. 183893 |
The original 2015 ordinance gave soft-story owners 1 year for plans and 2 years for permits. Ordinance 184081 extended those to 2 and 3.5 years. The 7-year completion limit didn't change.
How LADBS sent the soft-story orders
LADBS sent soft-story orders in waves by building size, according to its program page:
| Priority | Buildings | Orders started going out |
|---|---|---|
| I | 16 or more dwelling units, 3+ stories | May 2, 2016 |
| I | 16 or more dwelling units, 2 stories | July 22, 2016 |
| II | 3+ stories with fewer than 16 units | October 17, 2016 |
| III | 9-15 units | July 24, 2017 |
| III | 7-8 units | August 21, 2017 |
| III | 4-6 units | September 25, 2017 |
| III | Condos and commercial | November 6, 2017 |
Each building's clock runs from service of its own order, plus any extensions granted. If you're buying a building that was in one of these waves, ask for the permit history and the certificate of compliance. Don't assume the work is done.
Concrete is different. LADBS says a concrete building in scope is subject to the ordinance whether or not LADBS has identified it, and the department is still identifying buildings. Owners can check a property's status on the LADBS Permit & Inspection Report.
What the order means for title, sale and appeal
Both divisions use the same administrative steps (Ord. 183893, Secs. 91.9305-91.9311 and 91.9504-91.9510):
- Service. The order goes to the owner shown on the last equalized assessment roll, by personal service or certified or registered mail. Not receiving it doesn't excuse the owner.
- Recording. LADBS records a certificate with the Los Angeles County Recorder stating that the building is in scope. Once the building is retrofitted or demolished, or found not to be in scope, LADBS records a certificate that terminates the earlier one.
- Sale. Transferring title doesn't change the compliance dates. The penalty section also reaches successors and assignees of the owner of record.
- Appeal. An owner can appeal the order to the Board of Building and Safety Commissioners within 60 days of service. The board must decide within 60 days, and there's a filing fee.
Tenants: notices, habitability plans and relocation
The retrofit ordinances tie into the city's rent rules:
- The owner must tell current and prospective residential tenants about the order in a format set by the Los Angeles Housing Department (LAHD), and must tell non-residential tenants in a format set by LADBS.
- If the city's Rent Stabilization Ordinance (RSO) requires it, the owner must submit a Tenant Habitability Plan to LAHD (LAMC 152.03B).
- If, on review of the Tenant Habitability Plan, LAHD determines that the work affects a unit's tenantability as defined in California Civil Code 1941.1, the owner must pay relocation benefits under LAMC 151.09G to affected tenants. The ordinance adds that doing the retrofit work does not by itself make a unit untenantable.
LADBS lists the LAHD Tenant Habitability Plan Unit at (213) 252-1464 for these questions. Qualified historical buildings follow the California Historical Building Code.
Penalties
Once an order is served, it's unlawful to maintain, use or occupy a building that hasn't been retrofitted under the division (Sec. 91.9311 for soft-story, Sec. 91.9510 for concrete). A violation is a misdemeanor and can also be handled through administrative enforcement. "Any person" includes the owner, lessor, sublessor, manager or person in control of the building. It doesn't include tenants. There's an exception while work is proceeding within the ordinance's time limits or approved extensions.
Help with the cost
LADBS links to the Earthquake Multi-Unit Retrofit (EMR) grant program run by the California Residential Mitigation Program (CRMP). Per the LADBS page, EMR covers multi-story wood-frame residential buildings built before 1991 with 5 to 10 units and tuck-under parking, retrofitted to FEMA P-807, IEBC Chapter A4 or ASCE 41. Check eligibility and open dates on the program's site. Funding windows change.
Where insurance fits
Insurance doesn't pay for the mandated work
A retrofit order is a code requirement. Property policies pay for sudden physical loss, not for bringing a building up to a standard that a city requires on a schedule. Budget the engineering, permits and construction as a capital project.
During construction
Retrofit work often means opening ground-floor walls, adding steel moment frames and new foundations, and working around occupied units and parked cars. That raises the chance of property damage, injuries and claims from tenants.
- Require the contractor and engineer to carry adequate limits. Get certificates and be named as additional insured on the contractor's general liability and umbrella. See contractor additional insured requirements.
- Tell your property carrier about the project before it starts. Some policies restrict coverage during major structural work. Larger jobs may call for a builders risk policy.
- Your own commercial umbrella sits above your liability policy if a tenant or passerby is hurt.
Lost rent and relocation costs
Units emptied for retrofit work aren't a covered cause of loss, so relocation payments and rent lost during a planned retrofit are owner costs. Loss of rents or business income coverage responds when a covered loss, such as a fire during construction, makes units unusable. Check the waiting period and the length of coverage.
The earthquake itself
Standard property policies exclude earthquake shaking. Owners usually buy earthquake coverage separately. See commercial earthquake insurance and earthquake insurance in Los Angeles. After a retrofit, send the engineer's report and the certificate of compliance to your broker so underwriters see the upgrade.
Rebuilding to current code
If a covered loss damages the building, the city can require that repairs meet current code. Those extra costs fall under ordinance or law coverage. Check the limit, because it's often a percentage of the building limit.
Condo boards and building types
Condo associations deciding how to fund a retrofit, or whether to make special assessments, face owner disputes. That's the job of directors and officers coverage and the condo association policy. See also apartment building insurance in Los Angeles, mixed-use building insurance, office building insurance and parking garage insurance.
Retrofit checklist for Los Angeles owners
- Check scope. For wood frame, check stories, construction date and ground-floor openings. For concrete, check the original permit application date against January 13, 1976 (the date in the city code; LADBS's program page says January 13, 1977), even if you never got an order.
- Find the order date. Every deadline runs from service of the order. Look for a recorded certificate in the title report.
- Calendar every step. For soft-story: 2, 3.5 and 7 years. For concrete: 3, 10 and 25 years. File an appeal within 60 days if you think the building is out of scope.
- Handle tenant paperwork early. Send the required notices and file a Tenant Habitability Plan if the RSO applies.
- Before construction, collect contractor certificates, tell your property carrier, and decide whether you need builders risk.
- After completion, get the termination certificate recorded and send the retrofit documents to your broker before your earthquake renewal.
- In a sale, ask for the permit history, the recorded certificates and any extension approvals.
Frequently asked questions
Which Los Angeles buildings need a soft-story retrofit?
Wood-frame buildings whose permit for a new building was applied for before January 1, 1978 (or, with no permit on file, that were built under codes enacted before that date), with parking or similar open space at ground level and one or more stories above. Residential buildings with three or fewer units used only as homes are excluded.
How long do I have after a soft-story order?
Two years to submit proof of prior retrofit or plans to retrofit or demolish, 3.5 years to obtain a permit, and seven years to complete the work, all counted from service of the order.
Which concrete buildings are covered by the Los Angeles non-ductile concrete ordinance?
Concrete buildings whose roof or floors are supported by concrete walls or columns, built under a permit application for a new building submitted before January 13, 1976 (the date in the city code; LADBS's program page says January 13, 1977). Detached single-family homes and duplexes are excluded.
Does selling the building change the retrofit deadline?
No. The ordinance says transfer of title doesn't change the compliance dates, and LADBS records a certificate with the County Recorder so buyers can see the order.
Do I have to pay tenant relocation for a seismic retrofit?
If LAHD determines, on review of the Tenant Habitability Plan, that the work affects a unit's tenantability under Civil Code 1941.1, the owner must pay relocation benefits under LAMC 151.09G. A Tenant Habitability Plan may also be required for RSO units.
Will insurance pay for my seismic retrofit?
No. A required retrofit is a capital cost. Insurance matters for liability and property damage during construction, earthquake damage, lost rents after a covered loss, and code-upgrade costs under ordinance or law coverage.