On a large Orange County project an underwriter wants four answers before quoting: whether the value goes on a completed value or a reporting form, what the delay coverage pays if a fire on site pushes the opening back, how the site meets the fire authority’s lumber-drop and fuel-modification inspections, and who the contract says buys the policy. Earthquake is a separate decision. My part is the insurance on the project; the building is the contractor’s.
OCFA’s inspections before materials arrive
The Orange County Fire Authority serves 23 cities, among them Irvine, Santa Ana, Tustin, Lake Forest, Mission Viejo, Rancho Santa Margarita, San Clemente and Yorba Linda, plus the county’s unincorporated areas; elsewhere it is the fire agency serving that city. Two OCFA guidelines dated January 1, 2026 set the order of work on a new project:
- Lumber drop inspectionBefore combustible building materials come on site, an OCFA inspector verifies that access roads, fire lanes and working hydrants serve the buildings under construction. Gates in the construction fence need a Knox padlock or a breakaway lock, and work on a site that falls out of compliance can be suspended until it is fixed.
- Phased sitesA tract or multi-building project that installs its permanent roads in phases needs a lumber drop inspection before each phase, with its own inspection fee. Temporary roads and hydrants can be allowed for model homes or a single custom home under 5,500 square feet, on an engineer-certified plan that OCFA inspects before materials arrive.
- Brush clearanceWhere a fuel modification plan is required, combustible vegetation must be cleared at least 100 feet from structures under construction, lumber stockpiles, generators and fuel tanks before lumber drops, and the sign-off goes to the building department before construction proceeds. A final fuel modification inspection comes before occupancy.
Builder’s risk underwriters write the same order into their terms: IRMI commentary lists on-site water supply and hydrants active before vertical construction among the conditions it has seen in builder’s risk proposals. I bind the policy to start no later than the first delivery and keep the OCFA sign-offs with the submission, because they answer the fire questions before they are asked.
Canyon sites and the wildfire code
OCFA requires a fuel modification plan for new homes, apartments, ADUs and commercial buildings in or next to a wildfire-risk area: State Responsibility Area land and the high and very high fire hazard severity zones in local responsibility areas. The wildfire construction standards that come with those zones were Chapter 7A of the California Building Code until the 2025 code cycle moved them into the California Wildland-Urban Interface Code, Part 7 of Title 24, in effect since January 1, 2026. OCFA also notes that a precise fuel modification plan may need approval from other agencies, the Coastal Commission among them, before its own sign-off; that belongs in the schedule and in the policy term.
- Insure the cost of building to the code, not the value of what stood there before. A house going back up in Trabuco Canyon after the September 2024 Airport Fire is new construction, valued at what it costs to build now. Why rebuild cost is the number to insure.
- Expect questions about the brush line and the stockpile. The clearance OCFA requires around lumber and fuel is the same thing a fire underwriter looks for in site photos.
- Know the fallback for fire. The California FAIR Plan lists residential and commercial buildings under construction from the ground up among the commercial risks it takes. It is a named-peril policy for fire, lightning and internal explosion, with vandalism available at extra cost, and its Division I commercial limits rose in 2025 to twenty million dollars per building and one hundred million per location. Builder’s risk is usually written on an all-risks basis, so theft, water and the other perils need their own answer.
Completed value or a reporting form
IRMI defines builder’s risk as property insurance for property in the course of construction, usually extending to materials in off-site storage and in transit as well as at the site. It can be written on a completed value form or a reporting form, and either way the estimated completed value of the project is the limit.
- Completed value is the usual form for a single apartment, commercial or custom-home project: the limit is the expected finished value, sometimes with a coinsurance clause. If costs run past the estimate, raise the limit as soon as you know.
- A reporting form suits a builder with many jobs going at once, such as homes rising across several tracts. Values are reported on the policy’s schedule, usually monthly, and a late report can leave a loss underinsured because the values keep climbing. New sites are typically declared within a stated number of days of starting.
- What goes in the value: the contract sum and changes, materials and equipment you supply yourself, excavation and landscaping, and, if you want them insured, overhead, profit and architect’s fees, which many policies leave out unless you ask. Land is not insured.
Soft costs and delay in completion
For an apartment or commercial developer, the repair bill after a fire on site can be smaller than the cost of the months lost. IRMI calls this delayed completion coverage: an optional part of most builder’s risk policies that pays lost income or specified extra expenses, such as additional interest and advertising, when covered property damage delays completion. It also goes by soft costs and delay in start-up.
- Name the owner. IRMI commentary says delay coverages should generally be reserved for the project owner, and newer delay endorsements carry their own list of named insureds; an entity left off that list can end up with a gap.
- Read the waiting period. Soft-cost deductibles are often written as days or weeks rather than an amount.
- Match the list to your costs. The optional soft-costs coverage in the AIA’s 2017 insurance exhibit lists construction loan fees, leasing and marketing expenses, extra professional fees and carrying costs such as property taxes and additional loan interest. If lost rent is the exposure, ask for rental value coverage by name; it pays rent lost during the period of restoration.
- Bring the lender in early. Some loan agreements require the lender to be protected as an insured or loss payee.
Delay coverage answers to covered physical damage. A slow plan check or a late inspection is not a covered cause.
Who buys it, and where the wrap-up fits
The construction contract decides who buys builder’s risk, and the two common form families start from opposite ends:
- AIAAIA Contract Documents says the owner usually, but not always, buys the project’s property insurance, and its 2017 insurance exhibit lets the parties shift that duty to the contractor. As drafted, the exhibit calls for a builder’s risk all-risks completed value form covering the whole project at replacement cost, with the owner, contractor and subcontractors as insureds and mortgagees as loss payees.
- ConsensusDocsSince its 2017 revisions, ConsensusDocs says builder’s risk defaults to purchase by the constructor rather than the owner.
As drafted, the AIA exhibit also says the policy shall not exclude earthquake or flood, and it leaves a blank for sub-limits by cause of loss. In California that blank is where the earthquake conversation belongs, before anyone signs.
On a wrapped project, IRMI describes the controlled insurance program as one party buying insurance for most of the parties working on site, almost always workers’ compensation and general liability when cost savings drive it. Whether builder’s risk sits inside the wrap or beside it is a separate contract term, so read both documents (how wrap-ups work; the contractor’s own program). The contractor’s general liability is a policy of its own and does not insure the building going up.
Earthquake on an Orange County project
Builder’s risk forms commonly exclude earth movement and flood, and both are generally available by endorsement or in separate policies. Where it can be found, difference-in-conditions coverage is the usual way to add earthquake over a high deductible, and the earthquake deductible may be a dollar amount, a percentage of value, or both. The California Earthquake Authority is not a construction-period option: it sells homeowners, condo unit owner, mobilehome and renters policies through the home insurers that participate. On a custom home, earthquake becomes a homeowners decision once the house is finished and insured. Commercial earthquake insurance.
What to send me
- The address and the project type: apartments, commercial, mixed use, custom home or rebuild.
- The contract’s insurance section, or the AIA or ConsensusDocs exhibit as it will be signed.
- Completed value, with owner-supplied items, overhead and profit, and design fees shown separately.
- Schedule: first delivery, phases, testing, completion and first occupancy.
- OCFA status: fire master plan, fuel modification plan and lumber drop inspection dates.
- Soft costs: construction loan terms, projected rents or income, and the lender’s insurance requirements.
- Site security: fencing, cameras, guard service and where materials are stored.
Common questions
Who insures builder’s risk on large projects in Orange County?
I place builder’s risk for owners and contractors on apartment, commercial, custom-home and rebuild projects across the county, with insurers that write construction risks. For fire on a hard-to-place canyon site, the California FAIR Plan lists buildings under construction among the commercial risks it takes.
When should builder’s risk start on an OCFA project?
No later than the first delivery of combustible materials, which in OCFA territory comes after the lumber drop inspection. A stockpile on the lot can burn or disappear the first night.
Will builder’s risk pay my construction loan interest if a fire delays the project?
Only if the policy includes delay in completion or soft-cost coverage, which IRMI describes as optional. The owner should be a named insured on that part, and the waiting period should be read before you bind.
Is earthquake covered on builder’s risk in California?
Usually only if it is added by endorsement or bought separately. Check the contract first: unless the parties edit it, the AIA’s 2017 Exhibit A says the policy shall not exclude earthquake.
Who buys builder’s risk, the owner or the general contractor?
The contract decides. AIA Contract Documents says the owner usually buys it; ConsensusDocs says its forms default to the constructor.
Does a wrap-up cover the building while it is under construction?
Not necessarily. Wrap-ups are built around workers’ compensation and general liability, so check whether the sponsor also bought builder’s risk or left it to the contract.
General information about builder’s risk insurance for Orange County construction as of November 2026, not legal advice. OCFA guidelines, fire hazard maps, the state codes and standard contract forms change; confirm requirements with OCFA or the fire agency serving your city and with your building department, and read your own contract and policy wording. Coverage depends on underwriting and the terms, conditions and exclusions of the policy actually issued.